Operating certificate fees for solar installations 200kW-1MW
Service | Fee payable $ |
---|
1 July 2022 to 30 June 2023 | 1 July 2023 to 30 June 2024 | 1 July 2024 to 30 June 2025 | 1 July 2025 to 30 June 2026 |
---|
Grant of operating certificate – Assessment of application and supporting information*
|
200 kW to < 1 MW
|
1,243.10
|
1,289.75
|
1,334.90
|
1,381.60
|
Grant of operating certificate – Inspection by electrical inspectorates
|
200 kW to < 400 kW
|
2,219.40
|
2,302.65
|
2,383.25
|
2,466.65
|
400 kW to < 600 kW
|
3,329.20
|
3,454.00
|
3,574.90
|
3,700.00
|
600 kW to < 800 kW
|
4,438.90
|
4,605.35
|
4,766.50
|
4,933.35
|
800 kW to < 1000 kW
|
5,548.60
|
5,756.70
|
5,958.15
|
6,166.70
|
Grant of operating certificate – Reinspection and reassessment (if applicable)
|
200 kW to < 1 MW
|
1,489.90
|
1,545.75
|
1,599.85
|
1,655.85
|
Regulatory activities in relation to audit and compliance of an operating certificate – per hour
|
200 kW to < 1 MW
|
245.20
|
254.40
|
263.25
|
272.50
|
Operating certificate fees for unlicensed regulated utilities providing regulated utility services (other than solar installations 200kW - 1MW)
Service | Fee payable $ |
---|
1 July 2022 to 30 June 2023 | 1 July 2023 to 30 June 2024 | 1 July 2024 to 30 June 2025 | 1 July 2025 to 30 June 2026 |
---|
Grant of operating certificate – Assessment of regulatory Plan - per hour
|
245.50
|
254.75
|
263.65
|
272.85
|
Annual fee – Review of annual performance reports for compliance with conditions of the operating certificate – per annum
|
920.70
|
955.25
|
988.65
| |
Regulatory activities in relation to audit and compliance of an operating certificate and development or amendment of technical codes – per hour
|
245.50
|
254.75
|
263.65
|
272.85
|
*This fee is for assessment of an application and is non-refundable.
Please note: GST does not apply to operating certificate fees.